Motorola Project Update
a. ASTRO 25 7.11 Controller Upgrade Digital Controller Complete
i. Scheduled for July 2012
b. Winstar IR Site
i. Fully operational
ii. Site will be converted to P25 is the summer of 2012
c. Cherokee Marshall Service
i. 60 handheld and mobile radios
ii. Conventional 800 MHz repeater
iii. Implementation schedule it TBD
d. Troop C Console Project
i. Equipment has been received and is ready to be deployed upon
confirmation of installation location
ii. DPS is in negotiations for colocation in Muskogee 911 Facility
e. DPS Rebanding Project
i. Notice to proceed has been issued to Motorola1. Face to face meeting is scheduled to confirm DPS reconfiguration
implementation schedule
2. Coverage Testing is scheduled for May 2012
3. Infrastructure reconfiguration will begin upon completion and
evaluation of coverage testing
4. This will be coordinated with other Sprint rebanding projects
http://www.ok.gov/okwin/documents/OKWIN - Executive Committee - Meeting Minutes - (03.09.12).pdf