It looks like OpenSky is to be used in Milwaukee--like it or not. I hope for the Police Officers sake that the system does well for them in the end and hope the learning curve doesn't take too long for them to get used to. No one needs to die or get hurt over a radio system.
Nothing like trying to reward a contract at the end.
"The original RFPrequired 95% mobile and outdoor portable coverage across the service area
defined as the county. Portable in-building voice coverage (assuming 12 dB penetration loss for the
structures) is required by the RFPto be provided to at least 95% of the specified service area within the
legal boundaries of the City of Milwaukee. Federal Engineering will work with Harris and MPD to
determine the baseline coverage delivered by Harris and will also make recommendations on the best
way to improve coverage in marginal areas of the city. There are discussions currently taking place
between MPD and Harris about adding two additional repeater locations using existing towers to
improve overall coverage."
I like how the RFP goes from 95% within the county to 95% with in the legal city boundries.
Now they are thinking about installing BDAs when they should have known about the problem before. What lovely support MPD getts for the local shop.
Sounds like the original contract required;
1) 95% mobile coverage countywide.
2) 95% portable coverage, plus 12 dB margin for building penetration within the city.
The BDAs appear to be an additional solution to specific coverage issues not anticipated in the contract.
Sounds like the original contract required;
1) 95% mobile coverage countywide.
2) 95% portable coverage, plus 12 dB margin for building penetration within the city
The BDAs appear to be an additional solution to specific coverage issues not anticipated in the contract.
I like this part...
"In hindsight, a police department the size of Milwaukee, which generates
approximately 28,00 push-to-talk transmissions each day, took a significant risk in being one of the first
major cities to move to this technology"
Why would a big city take a risk like that, when there were so many other choices out there?
Other agencies do it. Washington county did specific site testing for their new P25 system.
This project was a cluster **** from the begining. Too bad they are to deep into now.