August 2, 2005 - Mayo Civic Center - Southeastern ARMER (re-)kickoff meeting. Representatives from the State, and all the vendors that make 800MHz (P25) portable and mobile radios will demonstrate their equipment.
Waiting for Antennas and Cabling.
Waiting for DC Power equipment.
Waiting for console upgrades at the Rochester/Olmsted 911 Center.
Waiting for connectivity to the West Metro "Zone Controller."
Waiting for the Viola single-site system to be enabled and tested.
Fleetmapping is nearly done, but at least one additional meeting is needed.

---

July 2005 - Pleasant Grove tower is competed, and equipment is installed.
Antenna and cabling is delivered, and installed at Viola and Pleasant Grove sites.
A portion of the Rochester/Olmsted system is turned on and tested.



http://www.semnradio.org/SystemStatus.shtml
 