update to stars
Check the state police website, its kept up to date of when frequencies will be active...ill list them below but they continue to change.
As of April 21 2008:
Operational Stages:
* Richmond (Division One) was operational as of December, 2005. Construction of an additional site which is being added to enhance coverage will begin April, 2008 once all regulatory approvals have been received.
* Chesapeake (Division Five) was fully operational as of March, 2008.
* Culpeper (Division Two) is projected to be completed and the Division operational by October, 2008.
* Fairfax (Division Seven) is projected to be operational February, 2009 including a unified dispatch center with Fairfax County and VDOT.
* Salem (Division Six) is projected to be operational April, 2009.
* Appomattox (Division Three) is projected to be operational November, 2009.
* Wytheville (Division Four) is projected to be operational December, 2010.