TCERN Project Update – Project Schedule • Fleetmapping April 15, 2021 • Manufacturer’s Equipment Staging • Microwave May 7-13, 2021 • LMR Infrastructure June 21-25, 2021 • Civil Site Work Now thru April 2022 • Installation • Microwave June 2021 thru April 2022 • 700 MHz System • Dispatch Consoles July 2021 thru October 2021 • Subscriber Installation October 2021 thru April 2022 • Training – End User February 2022 thru April 2023 • 700 MHz System Cutover June 2023