I can help clarify ISSI test TGs. I'll mention this is the first ISSI link of its kind to ever go live, it came up around 9am Wednesday morning.
Final ISSI pre-testing is happening now in preparation for a full and formal test Monday 7/19 between 1-4. You'll hear some interesting traffic during those hours. We're doing a battery of tests, including pulling the link to simulate a backhoe fade.
There are the 5 pairs of talkgroups (I just saw someone already corrected, here are loaded names, anyway

51000-60020 -NCTESTA
51001-60021 NCTRG-A
51002-60022 NCTRG-B
51003-60023 NCTRG-C
51004-60024 NCTRG-D
TESTA is a test talkgroup only, obviously, other four are being tested to validate ISSI deployment but will be moved to (4) new NCTCOG RF sites this fall.
I'll be running the tests, maybe I'll shout out to y'all ;-)
Cynthia