n4voxgill
Silent Key
The Philadelphia Inquirer has an article that starts:
PITTSBURGH - A statewide radio transmission system meant to allow various rescue agencies to communicate with one another during an emergency will be more than $180 million over budget when it is completed in about three years, officials say.
The state has been working on the project for 10 years and has spent nearly $311 million on it, officials said, well more than the projected $179 million. When the project is completed, the total bill is expected to top $360 million, in part because of added expenses after the Sept. 11 attacks
and ends up with:
Part of the added costs of the radio system resulted from new demands it had to meet after the Sept. 11 attacks, increasing the price per square mile from $7,000 to $30,000, officials said.
But another reason for the delay is that the construction company hired to build the towers went bankrupt, halting all work for nine months.
Workers are nearly halfway done constructing the more than 1,110 towers needed for the system to be in full operation, but the state is still trying to get all the land it needs to complete the project.
Here is the whole story:
<http://www.philly.com/inquirer/local/pa/montgomery/20070402_Pa__radio_system_way_over_budget.html>
So MACOM is not the only cause for the delay. It is hard to believe that state has not lived up its part of the contract by providing the towers.
PITTSBURGH - A statewide radio transmission system meant to allow various rescue agencies to communicate with one another during an emergency will be more than $180 million over budget when it is completed in about three years, officials say.
The state has been working on the project for 10 years and has spent nearly $311 million on it, officials said, well more than the projected $179 million. When the project is completed, the total bill is expected to top $360 million, in part because of added expenses after the Sept. 11 attacks
and ends up with:
Part of the added costs of the radio system resulted from new demands it had to meet after the Sept. 11 attacks, increasing the price per square mile from $7,000 to $30,000, officials said.
But another reason for the delay is that the construction company hired to build the towers went bankrupt, halting all work for nine months.
Workers are nearly halfway done constructing the more than 1,110 towers needed for the system to be in full operation, but the state is still trying to get all the land it needs to complete the project.
Here is the whole story:
<http://www.philly.com/inquirer/local/pa/montgomery/20070402_Pa__radio_system_way_over_budget.html>
So MACOM is not the only cause for the delay. It is hard to believe that state has not lived up its part of the contract by providing the towers.
Last edited: