go live date is first quarter of 2024 for 700mhz
TCERN Project o Project Schedule - There are no changes to the current P25 cutover date in the first quarter of 2024. o Civil Site Work - There are five sites still in the permitting process. o Site Leases – TCOMM is continuing to work on the Dupont site lease with JBLM and tower owners. The Joint Spectrum Center anticipates a 14-week process to do a spectrum analysis. At the end of December or beginning of January, TCOMM will reach out to get an update on the timeline