Logged talkgroup 1271 on site 5 yesterday.
Which would translate to 4f7 in HEX. TFS East Ops
Logged talkgroup 1271 on site 5 yesterday.
http://www.tpsb.ca/documents%2***endadoc.pdf
excalibur according to the document I have...
full integrated system will be ready january 2015
and the analog system will be decommissioned 1 year later, upon request from the board
and agreement with motorola contract with the new system.
So I don't know where this sept 2014 date is coming from, pulled out of thin air
Keep in mind unlike these aren't hard deadlines, if there are bugs in the system it can take months longer than expected or if no bugs things go faster, I don't Toronto is doing a hard switchover like Hamilton, they are migrating so perhaps by January all of the migration will be done, the old system stays powered up just in case of a failure of the new system.