Migration Vision:
• Truly interoperable P25 system
o Worcester wishes to maintain the option to procure from multiple vendors in the future without compromising basic system functionality
• Re-use of existing 800MHz frequencies
• Re-use, where feasible, of existing investments.
• Solid in-building coverage as a rule with BDA/DAS as a rare exception.
• High degree of redundancy at all system levels
• ISSI connections to FiRST & adjoining systems.
Timeline:
• RFP Released on April 7th, 2015
• Proposals due by June 22nd, 2015
• Oral Presentations (potential) week of July 6th, 2015.
• Recommendation to County Commissioners for action at first August meeting.
• Contract award / signing tentative in September, 2015
• System Acceptance by August 31, 2017.
• Full EDACS decommissioning by January 2018.