Amending what I wrote above, not all licenses are listed in the RRDB. Attaching some documents detailing the current status and plans for system construction and implementation.
From documents filed with the FCC:
Construction Outline And Time Table
Powhatan will be building out a total of 7 RF sites and 1 MW site for this system. With regard to implementation, scheduling, and time tables:
Currently, Powhatan County is building Two (2) towers with new equipment buildings and generators in place for each tower. Moreover, Six (6) existing tower are being are in the process of being designed to provide desired RF coverage.
These towers will also have new equipment shelters and stand-alone generators. Specifications for radio equipment have designed by our agency, working with Altairis Consultants and pre and post engineers with our LMR vendor, L3 Harris.
It is the County’s desire and intent to fully complete the system on or before January 2024.
To that degree, the extended implementation target plan is as follows:
- Complete the First Two (2) towers and new equipment buildings by December 2021
- Installation of subscribers by January 2022.
- Finalize interoperability talk options with surrounding public safety agencies, March 2022
- Complete installation Six (6) towers with new equipment, shelters, and generators by March 2023.
- Coverage testing August 2023
- Final acceptance December 2023
Towards that end, The County of Powhatan is requesting a build-out extension construction
deadline date of January 1, 2024, which would be consistent with our other callsigns:
WRFR474 WRDD912
This schedule doesn't seem to jibe with the coverage testing mentioned in the Facebook post.
Docs attached.