Saw the following posted on the radio committee web site. Anyone have any updates on what frequencies will be used, control channels?
https://sites.google.com/site/rensselaercountycommunications/home
ADVISORY TO ALL RENSSELAER COUNTY FIRE DEPARTMENT AND EMS SQUADS
COMMUNICATIONS PROJECT BRIEFINGS ARE UNDERWAY.
ALL CHIEFS AND SQUAD CAPTAINS HAVE BEEN NOTIFIED BY EMAIL.
THE PROJECT SCHEDULE HAS FIRMED UP AS FOLLOWS:
+ Motorola will begin final Fixed Network Equipment installation and testing the week of June 5 and is expected to be complete by August 1.
+ Functional testing will continue until the operational date is set.
+ The VHF Paging System will be tested during August and is expected to go on-line in September.
+ New System training will start after Labor Day and continue until all FD's and Squads have received training.
+ New portables will be distributed at training.
+ The new 800 System is expected to go operational in October at a date to be set.
Questions can be directed to any Radio Committee Member or Bureau Management Staff.